Greenbuild


16 June 2022 - Upside down and backwards


Because of improved airtightness, mechanical ventilation systems are becoming more usual in Ireland.
Therefore, the Building Regulations were changed to require that ventilation set-ups should be checked by an independent third party - the 'Ventilation Validation' procedure.

Now, in some ways, this seems like over-kill. Ventilation can't be that hard, is it?

Greenbuild normally talks about a 4 step procedure for the ventilation set up:

  1. It is designed
  2. It is installed
  3. It is commissioned
  4. It is tested (validated)

The first 3 steps can be the same company or individual, but the forth step should be an outsider. That is the role Greenbuild plays, along with other validators on the NSAI Ventilation Validation scheme.

So far so good.

Of late, we have come across 2 sites with centralised machines, where the install is upside down or back to front!

On one site, 16 of 20 extract-only units were upside down - thereby pushing air into the house, rather than pulling it out. That would have meant the smells and moisture being pushed around the house, rather than being taken out.

That wasn't great. Worse, maybe, was that on a later visit to the same site, lesson having been learned from that batch of 16, 4 of 8 houses on another road had the central extract machine upside down again.

At least that doesn't happen to centralised heat recovery systems....or does it?

Yesterday, we were validating a HRV home when it became clear that all the extracts were supplies and vice-versa. The unit had been ducted wrong.

One of the principal checks of the Ventilation Validation scheme is that flow rates are correct - except as we have found, they can be correct in volume but the wrong direction!


16 June 2022 - Vent Register Placement


In the same test visit as the HRV validation visit mentioned in the previous blog entry, 2 houses on this estate had issues with the vent placement. Almost exactly 2 years ago in the Greenbuild Blog we mentioned about register placement: 2020 Blog page - see the note from 21 June 2020.

Example of vent register that had to be moved  - no way to get the measuring device inA vent register that was placed too close to the main wall - when the mock fire breast was installed, it covered over the vent - no way to commission or validate it Example of vent register that had to be moved  - no way to get the measuring device inA vent register that was placed too close to the main wall - when the kitchen cabinets were installed, they covered over the vent - no way to commission or validate it, or for it to even work properly Example of vent register that had to be moved  - no way to get the measuring device inA vent register that was placed too close to the main wall - when the kitchen cabinets was installed, they were too close to it - no way to commission or validate it

As can be seen, much the same issue three times, and a headache for the installers to fix.

 

  Current Year
Previous Blog Entries...
2023 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012

Airtightness testing - IS EN9972:2015 Certified Member of the Irish Passive House Association


Greenbuild Energy Rating and Building Information Services Ltd trading as
GreenBuild
Gorey, Co. Wexford
Tel: 087 2521032   contact@greenbuild.ie
All information presented here is without warranty or guarantee.