Greenbuild

12 November 2013 - Airtightness of Blockwork - Part 3

Further to the previous blog posting, another interesting aspect of blockwork airtightness, in this case, after a scratch coat has been applied.

Scratch coat, and drilled insulation holes - The new OSB?

We have recently tested a couple of houses under construction, where the main wall structures are blockwork, with internal sand and cement scratch coated, which will then be skim coated.

The preliminary test has been undertaken before the skim coat. This was interesting as numerous block built houses have a scratch coat like this to improve airtightness, even though a plasterboard or insulated plasterboard is going afterwards on as the main wall finish.

What we found was that in one of the houses, the scratchcoat was not fully airtight. Even though the estimated leakage was only ca 15 m3/hr, on a house with a low result, that can make a significant difference.

The other house had a better scratch coat, but the drill holes all leaked. These were the holes that had been filled after the bonded bead insulation had been installed. Every single one of them. Each leak is only small, but as there may have been 60 or 70 holes or more, the total is again significant.

membrane covering some of the scratch coatThe scratch coated wall that was leaking a little one of the bonded bead insulation drill holes that leakedOne of the insulation drill holes that leaked - some were worse than this, others not as bad.

Lesson? Normally, if going for a very good airtightness result (e.g. Air permeability q50 of less than 3 m3/hr.m2) then a scratch coat like this is fine. In this case though, the builder was aiming for 1 m3/hr.m2 or less, so the results, at somewhat less than 2 m3/hr.m2, but still somewhat more than 1 m3/hr.m2 are disappointing.

On the other hand, in this case the skim coat will make up some of the shortfall - that will not be the case for every project that is depending on a scratch coat of plaster as the airtightness layer. That makes it a bit like the OSB story of the last few years.


16 September 2013 - Airtightness of Blockwork - Part 2

Further to the previous blog posting, we have recently been called back to do a quality check on a house tested late last year, as renovations are underway.

This is interesting, as it further shows how blockwork can affect the airtightness of a house.

Before and (not quite) after

This particular house had insulated drylined walls, but the occupants were never that happy with the thermal comfort of the house. The airtightness testing identified a number of airtightness issues.

As we suspected, and as can be seen from the picture of work in progress, the band of perimeter sealant/adhesive was never applied to each drylining board, allowing whatever air infiltration would occur in the blockwork to just find its way out at skirting board level, or via sockets and switches.

view of wall as was
A view of one of the walls as it was prior to the renovation
view of wal under renovation showing adhesive patches on wall
View of the same wall under renovation - the stains from the adhesive are clearly visible, and they also clearly do not mark out the perimeter of each board, as would be expected if the guidance in the Technical Guidance Document, Building Regulations Part L were being followed.

Lesson? As before, if going for a very good airtightness result (e.g. Air permeability q50 of less than 3 m3/hr.m2) then factor in having to seal off the blockwork, even if it is being covered over by a plasterboard or wooden finish - a coat of sand/cement or a specialist product such as Gyproc Airtite could be considered.


8 May 2013 - Airtightness of Blockwork

Many people are surprised when the airtightness rate of their project is worse than expected.

If it is a block built project, then the problems are often because the 'grain' of the blockwork is not sealed properly.

In some cases of fair faced blockwork, several coats of paint may suffice, but usually a coat of plaster or an airtight render is what is required.

Typical Blockwork Problems

junction of external plastered wall with internal wall, tied inJunction of external plastered wall with interal wall, tied in internal wall about 1 meter in from where it ties into external wallInternal wall about 1 meter in from where it ties into external wall example of an upper floor joist built into wall, with lots of 'ventilation' around itExample of upper floor joists built into wall, with lots of 'ventilation' around them

The left and centre images above are from a block built dormer house. They show thermal anemometer readings greater than 0.00 m/s, indicating air movement in test conditions - even 1 meter into the building from the external wall! The house was much better than average with the result from the preliminary test at this particular house giving a q50 of less than 1.5 m3/hr.m2. The builders had been very careful even though it was their very first attempt at "airtightning" a house.

These images show the internal wall scudded and ready to be wet plastered rather than dry lined - the test was lined up at this stage as they hadn't realised that the air can infiltrate so far into the house via the internal wall blockwork.

Lesson? If going for a very good airtightness result (e.g. Air permeability q50 of less than 3 m3/hr.m2) then factor in having to seal off the blockwork, even if it is being covered over.


15 January 2013: Worst practise?..or 'The worst airtightness in Ireland'

In the last blog entries we looked at what is best practise in Ireland for airtightness, and some of our best test results to date.
(see this link for the older blog page).

Recently a colleague working in Sligo, Chris Spoorenberg from Ecoscan mentioned that he had tested a house with an airchange rate of 30 recently, which got me wondering, "What are the worst test results we have had to date?".

For info they are these! (arranged by the q50 result - the ACH table might be slightly different):

q50 result ACH result Type of building
Worst! 23.99 27.02 1970s bungalow, newly renovated but with suspended timber floor, now exposed to show the timber, and all the cracks in it
2nd 20.49 12.80 1850's large country house - note the good volume to area ratio, evident in large difference between q50 and ACH rates
3rd 19.38 21.74 1930s dormer bungalow renovated in 2000 - and probably much worse off for it
And of course, only a tiny fraction of older houses or renovated homes are tested - the title of "Worst airtightness in Ireland" may be somewhat worse than any of these!

 

  Current Year
Previous Blog Entries...
2023 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012

Airtightness testing - IS EN9972:2015 Certified Member of the Irish Passive House Association


Greenbuild Energy Rating and Building Information Services Ltd trading as
GreenBuild
Gorey, Co. Wexford
Tel: 087 2521032   contact@greenbuild.ie
All information presented here is without warranty or guarantee.